Number Description Due date Status
1 Inception report End of month 1 Submitted on time
2 1st Interim report 13 April 2012 Submitted on time
3 2nd Interim report 27 July 2012 Submitted on time
4 Draft final report 26 October 2012 Submitted on time
5 Draft Guidebook/RD Policy Manual 25 May 2012 Submitted on time
6 Draft Checklist 25 May 2012 Submitted on time
7 Workshop 22 November 2012 Held
8 Final report 21 December 2012 Submitted on time
9 Final Guidebook/RD Policy Manual 21 December 2012 Available online
10 Final Checklist 21 December 2012 Available online